The purpose of this notice is to inform potential service providers of Shropshire Council’s intention to bring to market its Local Electric Vehicle Infrastructure (LEVI)” · description
“…ervice providers of Shropshire Council’s intention to bring to market its Local Electric Vehicle Infrastructure (LEVI) fund procurement opportunity to deliver additional electr…” · description
⚡Charger Specification
Total chargepoints
550
Locations
mixed
Power
Up to 50kW DC
Funding
LEVI
Breakdown
Standard · 7kW
Standard · 22kW
Rapid · 50kW
classified 18 Jun 2026
Description
Overview
The purpose of this notice is to inform potential service providers of Shropshire Council’s intention to bring to market its Local Electric Vehicle Infrastructure (LEVI) fund procurement opportunity to deliver additional electric vehicle charging infrastructure (EVCI) in Shropshire.
The LEVI funding allows large scale deployment of EVCI by the private sector, under contract to Councils, specifically targeting delivery of an equitable charging network. Forecasts indicate that by 2050, EV adoption will be significant, with an estimated 90% of cars being electric (EVs) across both rural and urban areas. The aim of the Government’s LEVI Fund is to get ahead of this demand, ensuring that access to EVCI is not a blocker to the EV transition, particularly for residents who are unable to charge at home.
The Council’s intention is to appoint a service provider (or consortia) to supply, install, connect and operate the EVCI. The Council will utilise LEVI funds to de-risk delivery for the private sector service provider and support the installation of EVCI to meet the level of demand anticipated for 2035.
This is an initial market testing exercise to aid the Council in gathering information. It is not an invitation to tender or request formal expressions of interest. A procurement exercise is expected at a future point in 2026, with a view to a service provider being appointed in early 2027 and the first charge points being operational before the end of 2027. It is expected that there will be a 28-week competitive flexible procedure comprising a 4-week premarket engagement phase, a two-stage competition (PSQ and ITT), post tender dialogue , BAFO, final evaluation and moderation , standstill and contract award
Background to Charging Infrastructure and LEVI in Shropshire
As of October 2025, there were a total of 546 devices across Shropshire, some of which have been delivered under contract to the Council. Initial analysis indicates that more than 550 new devices can be delivered across the region utilising the LEVI Fund capital funding, doubling the number of devices.
Work is underway to determine suitable areas and sites for delivery of this scale of EVCI. Devices will be located either on-street or on council owned land in the majority of cases. Further details will be provided at procurement stage.
Approval was given to take forward the LEVI process at a meeting of the Shropshire Cabinet on 11 March 2026.
Outline of the Scope of Shropshire Council’s LEVI Scheme
The anticipated scope of the scheme, in brief, is outlined here:
The scope of installation will primarily include standard 7kW devices, with the option to incorporate:
22kW fast devices, where local network capacity and site conditions allow; and
A limited number of 50kW+ rapid devices, subject to local network capacity and site suitability.
To facilitate the procurement process, the Council intends to utilise the established documentation available from the LEVI Support body, and available on the NEVIS platform, as far as reasonably possible.
The service provider will be appointed under a concession contract where the Council grants the service provider the right to deliver, operate, own and maintain EVCI on Council-owned land or highways. A 15-year contract (with the option to extend by one year) is proposed, which is in line with market trends and recommended by the Department for Transport (DfT).
The Council intends to adopt the Heads of Terms recommendations and will seek an annual concession fee and/or a percentage revenue share which will be determined as part of the procurement process and after undertaking market engagement.
The Council will invest its £2,006,000 of LEVI Fund capital funding, alongside investment from the service provider.
Additional Procurement and Scheme Information
The Council has not finalised its approach to a lotting strategy and is actively considering whether to divide the opportunity into lots or to appoint a single supplier. This decision will be informed by our preferred sites and charging speeds, market engagement and further analysis over the coming months, ensuring that the final structure both attracts strong market support and safeguards the interests of Shropshire’s residents and businesses.
The Council is updating its EVI Strategy that sets out its vision for the future of EVI and EV transition across the region. This strategy will be made available to bidders.
Overview
The purpose of this notice is to inform potential service providers of Shropshire Council’s intention to bring to market its Local Electric Vehicle Infrastructure (LEVI) fund procurement opportunity to deliver additional electric vehicle charging infrastructure (EVCI) in Shropshire.
The LEVI funding allows large scale deployment of EVCI by the private sector, under contract to Councils, specifically targeting delivery of an equitable charging network. Forecasts indicate that by 2050, EV adoption will be significant, with an estimated 90% of cars being electric (EVs) across both…
Analysis
High confidence
Shropshire is lining up a fifteen-year LEVI concession to roughly double its public charging network, and it is testing the market now before a formal tender later in 2026. The full analysis separates the two figures that matter, the £2m of LEVI capital the council is putting in and the £108m estimated value of the concession itself, and explains what a concession means for who funds and owns the chargepoints, the 7kW-to-rapid device mix, and the lotting decision still up in the air that could shape who gets to bid.
Unlock the full analysis with Pro
See who should bid, the buyer’s profile and the competitor landscape.
Oldest first: procurement milestones and pipeline-detected changes combined.
📢
Originally Published
Procurement
Tender first published by Shropshire Council
OCDS release history
🔒
Submission Deadline
Procurement
Submissions due by 17/07/2026
🔄
Contract Start
Procurement
Expected contract commencement